Awesome City DPW work on Maplewood!

Catherine's avatarGood Morning Gloucester

What’s happening on Maplewood? Much of it is underground. Orchestrated crews are working on a huge project in a neighborhood that has been neglected for some time.

FAST STATS

Status: in progress

The work includes 4000 feet road resurfacing (July) and nearly 5000 feet of new sidewalk (both sides). DPW is working to make improvements to utilities as well: all new water services, a series of valves and some drain work. “National Grid is also replacing some aging gas mains and services.” 
Progress June 2017: nearing finish line
Project start: partial sidewalk begun last year
Funding Awarded: FY2017-18

  • from State: Balance of about $600,000K Chapter 90 funds
  • from City: $100,000K from CDBG and Community Development

Contract completion: part of City’s annual paving bid and on schedule.
Locations: downtown Maplewood Avenue. This work dovetails with larger water work “bid and awarded to Granese of Salem. They worked on…

View original post 65 more words