What’s happening on Maplewood? Much of it is underground. Orchestrated crews are working on a huge project in a neighborhood that has been neglected for some time.
FAST STATS
Status: in progress
The work includes 4000 feet road resurfacing (July) and nearly 5000 feet of new sidewalk (both sides). DPW is working to make improvements to utilities as well: all new water services, a series of valves and some drain work. “National Grid is also replacing some aging gas mains and services.”
Progress June 2017: nearing finish line
Project start: partial sidewalk begun last year
Funding Awarded: FY2017-18
- from State: Balance of about $600,000K Chapter 90 funds
- from City: $100,000K from CDBG and Community Development
Contract completion: part of City’s annual paving bid and on schedule.
Locations: downtown Maplewood Avenue. This work dovetails with larger water work “bid and awarded to Granese of Salem. They worked on the right hand side of Washington Street all spring (Riverside, Gloucester Ave, Whittemore and now moving to Grove and Derby see photo today) cleaning and lining water mains.”
Priority: Top Level! Mayor’s Office considers infrastructure and safety improvements a priority and walkability adding into quality of life benefits for residents, visitors and economy.
Upcoming streetscape work– Middle Street

GAS LINES

DRAINS

WATER