Annisquam River dredging 2020: closeup views from the boats and across to A. Piatt Andrew bridge #GloucesterMA

Here are some views across Annisquam River to A. Piatt Andrew bridge to show relative scale and position of the Annisquam River Dredging operation in February 2020. The Annisquam River dredging project began back in October 2019 and will continue into next year, however it’s not continuous. It’s overseen by the U.S. Army Corps of Engineers. The first dredging sections began in October 2019 (north of the 128 bridge, by Lobster Cove and Thurston Point), and will finish up next Friday (February 28, 2020), following two extensions. Dredging will resume sometime in the fall, likely October 2020.  They’re moving in the direction of the Cut right now. The operations run 24 hours a day with two 12 hour shifts. There are lots of local hires manning the rigs. Cessation by Friday is definite. “There won’t be a third extension because of the flounder spawning season,” says Paul Vitale, captaining one of the push boats for Patriot Marine, a Coastline Consulting sub-contractor.

The equipment you might see before they begin disappearing by the end of this week  are the following:

  • Three barge dredges operating excavators; one is a self loader designed to go in spots where there’s not enough space (There’s still a chunk to do between the train bridge and the cut bridge. The self loader will be doing that.)
  • Three dump scows (also barges) where they put the mud that they load into and cart away to very specific dump sites in Ipswich Bay (they have 5 or 6 compartments and doors that open up on the bottom like coal cars)
  • Roy Boys and Nancy Anne, two tug boats that do the dump runs primarily to Ipswich Bay, carting the scows back and forth
  • Three push boats – two manuevering with each dredge plus one (to help move or ready if there’s a breakdown)

When the project is completed, the U.S. Army Corps of Engineers will remeasure and update charts. Buoys will be in new spots. But that’s still a long way off.  Fun facts: the scooped sediment was sandier by Thurston Point and muddier at the bend where they’re situated now. There are sensors and computers linked up on barges and scows for monitoring the dump runs, and future research and tracking. The grants obtained for this massive dig were written long before the March trio of storms struck Good Harbor Beach and Long Beach.

 

Closeup views from the barges and vessels courtesy photos below:

 

Mayor Romeo Theken shared the City of Gloucester dredging announcement here November 8, 2019.

About the dredging:

The U.S. Army Corps of Engineers, New England District is proposing to perform maintenance dredging of the Annisquam River Federal navigation project (FNP) in Gloucester, Massachusetts. The city of Gloucester is the local sponsor and requested this dredging.

The proposed work involves maintenance dredging of portions of the 8-foot-deep Mean Lower Low Water (MLLW) channel and anchorage, plus authorized overdepth dredging in the Annisquam River FNP. 

“Natural shoaling processes have reduced available depths to as little as 1.0 foot in portions of the 8-foot MLLW channel and anchorage making navigation hazardous or impossible at lower stages of the tide,” said Project Manager Erika Mark, of the Corps’ New England District, Programs/Project Management Division in Concord, Mass. “Maintenance dredging of approximately 140,000 cubic yards of sand and some gravel from approximately 20 acres of the authorized project area will restore the FNP to authorized dimensions.”

A private contractor, under contract to the government, will use a mechanical dredge and scows to remove the material and then transport it for placement at the Ipswich Bay Nearshore Disposal Site (IBNDS) and the Gloucester Historic Disposal Site (GHDS). Approximately 132,500 cubic yards of sandy material will be placed at the IBNDS and the remaining 7,500 cubic years of sand and gravel material will go to the GHDS. Construction is expected to take between 3-4 months between Oct. 1, 2019 and March 15, 2020.

Proposed work is being coordinated with: U.S. Environmental Protection Agency; U.S. Fish and Wildlife Service; National Marine Fisheries Service; Massachusetts Office of Coastal Zone Management; Massachusetts Department of Environmental Protection; Massachusetts Division of Marine Fisheries; Massachusetts Historical Commission; Massachusetts Board of Underwater Archaeological Resources; Mashpee Wampanoag Tribe; Wampanoag Tribe of Gay Head (Aquinnah); and city of Gloucester harbormaster. An Environmental Assessment is being prepared.

The public notice, with more detailed information, is available for review on the Corps website at http://www.nae.usace.army.mil/Missions/Navigation/Public-Notices/.

Cranes, trucks, piers and parking lots! Maintenance and new construction on Stacy Blvd and Rogers St #GloucesterMa

What’s happening on Stacy Boulevard? That Department of Public Works (DPW) project involves the main interceptor sewer cleaning and inspection which is an every 7-10 year process.

At the western edge, Yella on the Water staff training took place outside on their new deck. They refurbished the parking lot and completed the accessibility ramp.

Along Rogers Street, Building Center and Gloucester House are busy with construction. A bit further down, DPW is improving the Rose Baker Senior Center parking lot, completing “just the binder for now, then on to ramps and finally top coat.”

Waterfront businesses require unusual maintenance like pier infratstructure maintenance. Gloucester House has been in business since 1958. I wonder how long the pilings last? The trio of wharf booths for special adventures there include Gloucester Boat Rental, the Thomas Lannon, & 7 Seas Whalewatch.