Stacy Boulevard Part 7: expanded garden plans Tulip Fest May 6, 2017

photos: © Catherine Ryan
Saturday May 6, 2017 is the official ribbon cutting re-opening of Stacy Boulevard by Mayor Romeo Theken. Thanks to the Mayor, Mike Hale and all Gloucester DPW, GZA, Essex County Landscape Assoc, Gloucester Community Preservation Act, Ann Giraldi Johnson, GFWA, Lieutenant Governor Karyn Polito, and groups like the Seaport Economic Council and Dir Carolyn Kirk, Department of Conservation and Recreation (DCR), Joe Lucido, Ed Parks, Mike Linquata, Donna Ardizzoni and One Hour at a Time Gang, Ringo Tarr, Bobbie Turner, YMCA and summer help, Wolf Hill, Generous Gardeners, and other volunteers!
Tulip Festival and bonnet parade Saturday 10AM
Ribbon Cutting 11:30AM
Party at Mile Marker Restaurant 6-10PM
Enjoy a closer look at the engineering and landscape plans for the expanded gardens and before/after comparisons.
Before April 2017 | After May 2017

















Funding for future perennials funded in part by the Gloucester Community Preservation Act

CPA grant towards new gardens summary of design and details

Series:
- Part 4 – Gloucester’s majestic public works construction stats: bringing the Stacy Boulevard plans to life
- Part 3- Gloucester’s Stacy boulevard public works construction Part 3: compare high res plans from 1922 and 1923 with today
- Part 2: Stacy Boulevard Public Works stunner | Gloucester is an early client for the Harvard and Olmsted trained landscape designer, Thomas Warren Sears. His 1908 photos are a must see!
- Part 1: STACY BOULEVARD NEARING THE FINISH LINE Part 1 – Walk this way: Gloucester’s stately Stacy Boulevard public works project is breathtaking and one for the ages!
- September 12 2016- Stacy Boulevard construction update: historic Blynman the Cut Bridge project scope plans and engineering details
- August 2016 Stacy Boulevard construction details. Gloucester DPW is impressive
Gloucester Smiles-590
Lonely Red – The “Good Luck Tulip”
Great poster with timeline and facts about the Stacy Boulevard Flag Display
Thanks to Ringo Tarr, Pauline Bresnahan, Cape Ann Veterans

Gloucester Smiles-597
Ceremonial Removal of the Last Fence section
Gloucester Smiles-571
Stacy Boulevard construction Part 5: rounded a big corner and an angle of repose

INVISIBLE DETAILS UNDERFOOT AND RIGHT THERE
Earlier posts outline the engineering. The photograph above details the subgrade that was re-established for irrigation (note ditch alongside walkway), loam and sod. The photo also emphasizes the lengthy short wall on the right which was removed for access during construction. “The excavation was deep enough that the angle of repose was into the old wall.” The wall in the photo is rebuilt.

MEMORIAL BENCHES
Spacing and symmetry were important design considerations for Stacy Boulevard construction. The old benches were surveyed. Most were returned relative to where they were sited before the build out. The memorial benches on the boulevard are full. This one shows a tribute to Al Swelka.



Photos Nov-Dec 2016. Video caption: Stacy Boulevard construction minute – stroll before January, and sod. Upcoming posts in this Stacy Boulevard series include: disasters, the cultural landscape, and Blynman.
Series:
Part 4 – Gloucester’s majestic public works construction stats: bringing the Stacy Boulevard plans to life
Part 2: Stacy Boulevard Public Works stunner | Gloucester is an early client for the Harvard and Olmsted trained landscape designer, Thomas Warren Sears. His 1908 photos are a must see!
STACY BOULEVARD NEARING THE FINISH LINE Part 1 – Walk this way: Gloucester’s stately Stacy Boulevard public works project is breathtaking and one for the ages!
September 12 2016- Stacy Boulevard construction update: historic Blynman the Cut Bridge project scope plans and engineering details
August 2016 Stacy Boulevard construction details. Gloucester DPW is impressive